Project Schedule

Progress bar
May 17, 2013

The project is approximately 92% complete.

Photo Gallery

Visit the Photo Gallery to view pictures as the project progresses.

View Photos >

Sign Up for E-Mail Alerts

Receive the latest news and alerts.

Sign up now >

Project Update

Comments Off
May 17, 2013 ·

South Section:

  • Asphalt binder course placement is complete on the west side of Walkup Road from north of Talismon Drive to south of Crystal Ridge Drive. Final surface course will be installed within the next several weeks.
  • Installation of the concrete handholes in the left turn lanes for signal wiring is complete. Mast arms (traffic signal poles) are currently being installed. Temporary pavement markings have been placed to help guide you through the intersection, please drive carefully and watch for intermittent lane closures at the intersection to facilitate signal pole installation.
  • Manhole final adjustments will occur next week. Use caution while driving through the area as construction barrels will be placed on some manholes that you will need to avoid while the concrete used for adjustments is curing.
  • The temporary traffic signal at IL Route 176 and Walkup Road will be deactivated and the newly installed permanent traffic signal will be activated on June 6th.
  • Multi-use path installation is complete along the east side of Walkup Road.
  • Sidewalk installation along IL Route 176 and Walkup Road is ongoing.
  • Landscaping will start next week.

North Section:

  • Paving of the final lift of asphalt is scheduled to be completed today.
  • Shoulder stone will be placed next week.
  • Permanent pavement striping is scheduled to occur next week.
  • Please be aware: the new traffic signal installed at Mason Hill Road and Crystal Lake Road is scheduled to be activated June 6th.
  • Temporary lane closures and flagger operations may be required at times so please slow down and proceed with caution.

Project Update

Comments Off
May 9, 2013 ·

South Section:
Binder course installation at the IL Route 176 intersection with Walkup Road was completed Wednesday 5/8. Final surface course will be installed within the next several weeks. Today (weather permitting) the contractor will prep for placing asphalt on Friday on the west side of Walkup Road from north of Talismon Drive to south of Crystal Ridge Drive. Work on the traffic signals will continue at the intersection with installation of the concrete handholes in the left turn lanes for signal wiring. In order to allow this handhole installation work to occur safely in the left turn lanes, traffic will be relocated to the outside lanes approaching the intersection while this work occurs.

Multi-use path installation will begin today along the east side of Walkup Road.

Landscaping will tentatively start late next week or early the following week.

North Section:
Paving of the final lift of asphalt is scheduled to begin next week and last approximately 1 week.

Temporary lane closures and flagger operations may be required at times so please slow down and proceed with caution.

Project Update

Comments Off
May 3, 2013 ·

South Section:
Curb installation on Walkup Road is complete and will be followed next week by asphalt placement, final striping, landscaping, and multi-use path construction.

Project work on IL Route 176 for the next week will consist of the grading of the area behind the curb, continued sidewalk installation and asphalt placement.

Traffic signal installation continues on IL Route 176 and Walkup Road.

North Section:
Traffic signal installation at Mason Hill Road is ongoing, but the signal will not be turned on for use until surfacing is complete and the final striping configuration is in place.

The remaining work on the North Section is final surfacing, striping, traffic signal installation at Mason Hill Road, and punch list cleanup. Paving is expected to begin within the next two weeks and will take approximately one to two weeks to complete.

See All Updates >